Wednesday, January 28, 2009

Electrical wiring


The electricians have installed the switchboard. Cables and conduits for power, phone and gas have been laid between the house and the street.
Posted by Picasa

Wednesday, January 21, 2009

Kitchen and Vanities


Our kitchen has been installed (not finished though). Here are the before and after photos.





And the vanities have arrived.

Posted by Picasa

Thursday, January 15, 2009

Fix out

Doors, architraves...

...and tiling have all begun.

Posted by Picasa

Monday, January 12, 2009

Deck and bath


Erina stained the deck on the weekend.

The bath was installed today
Posted by Picasa

Wednesday, January 07, 2009

Deck roof goes on!


The roof sheeting is now on the deck.
Posted by Picasa

Monday, January 05, 2009

Deck roof construction


Having built the floor of the deck we installed the posts and framed up the roof.
Posted by Picasa